In the City of Toronto, a sign fixed to your building needs a sign permit and a building permit before it goes up. The path is: get the landlord's written authorization, check the sign district for your address, apply by email with scaled drawings, pay the fee, install, then book a final inspection and hand the inspector an installer's report. The minimum permit fee is $334.53, and an application for three or fewer signs on a property without heritage designation is reviewed within three business days.

Those rules are Toronto's. Mississauga, Brampton, Vaughan, Markham and every other GTA municipality has its own sign by-law, with its own fees and steps. If your restaurant is outside the City of Toronto, start with that municipality's sign page.

Start with the landlord and the address

The City lists a letter of authorization from the property owner as always required, and it publishes no template. Ask for it when you negotiate the lease, along with any sign rules the building or plaza sets for its tenants. A landlord can refuse a sign the City would allow.

Then look up the address. Every property in Toronto is assigned a sign district that sets what is permitted there, and the City's SignView map shows the district and its rules. Do this before the sign is designed.

What needs a permit and what does not

The City's wording: any time a sign is installed on a building or into the ground, a sign permit and a building permit are required. Painted wall signs and window signs need a sign permit only.

Window signs have an exemption that matters to a restaurant. No sign permit is needed if the sign has no electronic copy, covers no more than 25 per cent of the window area, shows only first-party copy, and sits no higher than the second storey. First-party copy identifies the business on the premises. A full-window wrap falls outside that exemption and needs a variance before a permit.

The application

Applications are electronic only, sent by email as PDFs. The package includes the City's application forms, the owner's letter, and drawings to scale, fully dimensioned, signed and dated. Most signs other than window and painted signs also need structural information: loads, the weight of the sign and how it attaches to the wall. Your sign maker prepares this.

A property with three or fewer signs and no heritage designation is reviewed within three business days of the application being created in the City's system. Heritage-designated properties and applications for four or more signs do not get the three-day service.

The fees, as the City lists them

The minimum fee for a sign permit is $334.53, which includes a $70.67 building permit fee. Wall, projecting and window signs are charged at $37.71 per square metre, with a minimum of $253.72. A variance application for a first-party sign is $971.16.

A sign put up without a permit carries an administrative fee of $963.71 per sign face once a notice of violation is issued.

These are City fees only. They do not include the sign, the drawings or the installer.

Signs that hang over the sidewalk

A projecting or blade sign that sits partly over the public right of way needs written approval from Transportation Services as well as the permit. After the permit is issued you arrange an encroachment agreement. The City says these cost between $400 and $2,000 or more and may carry annual fees. Without one, the permit can be revoked.

Installation and the final inspection

The permit stays open until the City inspects. A final inspection is requested once the sign is installed, and a ground sign also needs a footing inspection before concrete is poured. Before the inspector can close the permit you must provide an installer's report: the address, the permit number, the installer's name and contact details, the installation date, and a signed statement that the sign matches the permitted plans.

Ask the sign maker to include the report and the inspection booking in the quote.

A-frame signs on the sidewalk

A sandwich board is a separate permit. The City charges $151.32 including HST for a new A-frame permit and $105.73 plus HST to renew. The sign can be no larger than 0.6 metres wide, 1 metre high and 0.75 metres long, unlit, and out only during business hours. You need proof of two million dollars in commercial general liability insurance, a letter from the property owner dated within 30 days, and a letter from the BIA if you are in one.

The sidewalk must keep a 2.1 metre pedestrian clearway, or 2.5 metres on certain downtown streets. A-frames are not allowed on Bloor Street between Avenue Road and Sherbourne Street, or on Yonge Street south of Davenport Road.

Common questions

Can the sign go up while the permit application is being reviewed?

No. The administrative fee for a sign erected without a permit is charged per sign face, and an outstanding violation can add fees to the application. With a three-business-day review for a simple application, waiting costs little.

Who should file the sign permit, the owner or the sign maker?

Either can. The structural details and the installer's report come from the sign maker in any case, so it is usually simplest for the sign maker to file. The landlord's letter is yours to get.

Does a coming-soon banner or hoarding graphic need a permit in Toronto?

We could not confirm the current rule on the City's pages, so we will not state one. Ask Toronto Building and your landlord before you print, and treat a full-window graphic as a window sign that falls outside the 25 per cent exemption.